10 January 2011 




 
construction started on site at the noordermarkt
 

construction started on site in the monumental building at the noordermarkt

The first preparations have been made: the monumental parts of the building are protected; the building site is arranged and the materials and suppliers have been selected

the contractor has commenced stripping the building, including the removal of the rooftiles in order to start the straightening the distorted roof structure.

on short-term the contractor will start building the new foundation

to be continued...